Velos IoT Planned Work Notification PW12535 - rescheduled

Scheduled Maintenance Report for Velos IoT Service Update

Completed

The scheduled maintenance has been completed.
Posted Oct 15, 2026 - 08:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 15, 2026 - 05:00 UTC

Scheduled

Our network vendor will be performing a maintenance work on their West SMSC Platform. Customer SMPP connectivity and SMS messaging service will continue via the East SMSC during the maintenance of West.

Service Impacted:
There will be a change of the IP point in the Firewall from West to East, that will lead all traffic to East SMSC.
Customers may experience:
- a brief disconnection and reconnection of SMPP.
- short delays in message delivery.
- temporary message queueing.
The delays expected to last only a few minutes.

Change Summary:
Isolating West SMSC
Start Time:
October 15, 2026 04:00 UTC
End Time:
October 15, 2026 07:00 UTC

The upgrade will be performed outside the Maintenance window and traffic will be reintroduce to West SMSC when upgrade finalized. Date and time will be announced in another maintenance message.

Completion Mediation:
Application-, Service-, Infra- and HA-Testing will be executed successful before traffic will be reintroduce.

Recovery Mitigation:
If recovery is required, the West SMSC will be restored to same level as before any upgrade is performed and traffic will be reintroduced.
Posted Oct 12, 2026 - 17:05 UTC